The Reconstruction Project


About the reconstruction project of Marine Fuel Terminal  "Turukhtannye Islands" (the Terminal)

Project targets

·         The Terminal annual throughput to reach more than 2 million tonnes.

·         The Terminal three berths to have a total length of over 450 meters with seabed level mark - minus 10 meters.

·         Overall storage capacity of FSOs - 15 tonnes.

·         Eight storage tanks of total capacity - 42 tonnes.

·         Two-lane railway overpass for the 28 oil tank cars of simultaneous discharge.

Project phases

·         2012- 2015: Project development and appraisal at Glavgosexpertiza; the facility site preparation.

·         2H, 2015 – 1H, 2017: Construction and commissioning of the Terminal.

·         As from 2017: Commencement of the Terminal operations (oil product transshipment).

Current developments

·         Reclamation work permits obtained from the Federal Marine and River Transport Agency for creation of artificial territory in the water body.

·         Site planning and boundary setting plans – approved. The Terminal development included in the territorial planning scheme of the Russian Federation.

·         Rail transport specifications – available; overhaul of railways scheduled for completion by the end of 2015.

·         Power supply specifications – available (power capacity at 3.4 mW).

·         Project documentation successfully passed state expert examinations with positive opinion of the State environmental expert review and of GlavGosEkspertiza.

·         Signing of reclamation contract, obtaining building permits scheduled for the end of 2015.